saperator-bg

12.9 MW cogeneration plant in Poland will be completely delivered by TEDOM

calendar 11.02.2022
On January 14, 2022, TEDOM Poland signed a contract for the “Construction of a cogeneration gas plant at Zakłady Górniczo-Hutnicze Bolesław S.A.” including the delivery of a trigeneration source fueled by natural gas.

This project, which received co-financing from the “Norway grants”, will produce 12.9 MW of electricity, 5.89 MW of heat in the form of hot water and 9.69 tons of process steam at a pressure of 6 bar and a temperature of 165 °C per hour. The installation will consist of three MWM TCG2032V16 gas generator sets in three TEDOM Quanto CHP units and three steam generators from APROVIS Energy Systems.

The CHP plant will be built at Zakłady Górniczo-Hutnicze Bolesław S.A. which processes zinc, in the city of Bukowno near Krakow in Poland. TEDOM will carry out the task in a consortium with INTROL ENERGOMONTAŻ Sp. z o.o. in the next 18 months.